Construction Update: November 7-November 21, 2012

Henley Construction Company reports that they have:
  • Delivered and set the chiller;
  • Continued with interior light gauge framing;
  • Finished stair 1 installation;
  • Began fabricating high roof panels;
  • Started low roof installation;
  • Finished roof blocking;
  • Continued electrical and plumbing rough-ins;
  • Finished interior CMU walls in basement area;
  • Started field measuring for windows; and
  • Started light monitor roof. 