Construction Update: April 12 to May 9, 2012

Henley Construction Company reports that they have:
  • finished footings and foundation wall in the basement area and on the north end of the building and completed necessary backfill;
  • continued working on the plumbing at the north end main level;
  • started plumbing underground in the basement, and completed the storm underground;
  • started extra work on the existing steel moving bar joists and stiffener plates;
  • continued working on removal of existing desk; and
  • mobilized electricians and materials on the site.

The construction project has been underway for 142 days.
Posted by R.Gale.
 