During these two weeks, Henley Construction Company:
  • continued interior building demolition;
  • changed the entrance to its construction offices;
  • finished sediment control devices and passed inspection;
  • finished tree protection devices and passed inspection;
  • arranged for the chiller to be removed from the site;
  • held a preconstruction meeting with the Department of Permitting Services Building Inspector;
  • and started mass demolition on the north end of the building.  