Construction Update: May 9 to May 23, 2012

Henley Construction Company reports that they have
  • finished slap preparation work in the basement;
  • finished plumbing underground in the basement;
  • continued plumbing underground in the north end; 
  • finished electrical underground work in the basement; 
  • back filled knee walls in the basement; and
  • started telecommunications duct bank work.

The construction project has been underway for 156 days.