Construction Update: June 6 to June 20, 2012

Henley Construction Company reports that they have:
  • finished plumbing underground in the north end;
  • finished electric underground in the north end;
  • installed the audio loop conduit;
  • prepared the slab on grade at the north end;  and
  • set the structural steel at the basement addition.
The construction project has been underway for 184 days.

Posted by R.Gale.
 

Construction Update: May 23 to June 6, 2012

Henley Construction Company reports that they have:
  • poured the basement slab;
  • formed and poured the curb and mechanical pads;
  • continued working on plumbing underground at the north end;
  • started electrical underground work at the north end; and
  • finished the telecom bank except for some back fill. 
The construction project has been underway for 170 days.

Posted by R.Gale.