Henley Construction Company reports that they have:
- finished plumbing underground in the north end;
- finished electric underground in the north end;
- installed the audio loop conduit;
- prepared the slab on grade at the north end; and
- set the structural steel at the basement addition.
The construction project has been underway for 184 days.
Posted by R.Gale.