Construction Update: May 23 to June 6, 2012

Henley Construction Company reports that they have:
  • poured the basement slab;
  • formed and poured the curb and mechanical pads;
  • continued working on plumbing underground at the north end;
  • started electrical underground work at the north end; and
  • finished the telecom bank except for some back fill. 
The construction project has been underway for 170 days.

Posted by R.Gale.
 