Henley Construction Company reports that they have:
- poured the basement slab;
- formed and poured the curb and mechanical pads;
- continued working on plumbing underground at the north end;
- started electrical underground work at the north end; and
- finished the telecom bank except for some back fill.
The construction project has been underway for 170 days.