Construction Update: August 2 to August 15, 2012

Henley Construction Company reports that they have:
  • finished backfill around the north end;
  • continued backfill work at the basement area;
  • completed waterproofing up to the brick shelf at the basement area;
  • completed the foundation drain at the basement foundation;
  • continued installing mechanical hangers in all areas, and
  • started the second floor electrical roughins at the slab on deck.

The construction project has been underway for 239 days.

Posted by R.Gale.