Henley Construction Company reports that they have:
- finished backfill around the north end;
- continued backfill work at the basement area;
- completed waterproofing up to the brick shelf at the basement area;
- completed the foundation drain at the basement foundation;
- continued installing mechanical hangers in all areas, and
- started the second floor electrical roughins at the slab on deck.
The construction project has been underway for 239 days.
Posted by R.Gale.Labels: Construction, Gaithersburg