Construction Update: August 30 to September 12, 2012

Henley Construction Company reports that they have:
  • continued perimeter channel framing; 
  • finished the slab preparation for the main and second floor;
  • completed installation of stairway two;
  • poured the concrete slab on the main and second floor decks;
  • poured a portion of stairway two;  
  • continued with duct hangers on the south end; and
  • began work on the PEPCO duct bank.

The construction project has been underway for 267 days.

Posted by R. Gale

Wednesday, September 5, 2012

Construction Update: August 16 to August 29, 2012

Henley Construction Company reports that they have:
  • finished backfill of the exterior basement walls; 
  • completed the slab on deck rough ins for the north ends of the main and second floor;
  • set the steel on deck at the floor and roof above the newe electric room;
  • continued to work on installing steel on deck in all areas;
  • continued installing electric hangers; and 
  • started the plumbing prep at the slab on deck on the second floor.

The construction project has been underway for 253 days.  The major news is that the framing for the roof structure has begun.

Posted by R. Gale