Henley Construction Company reports that they have:
- continued perimeter channel framing;
- finished the slab preparation for the main and second floor;
- completed installation of stairway two;
- poured the concrete slab on the main and second floor decks;
- poured a portion of stairway two;
- continued with duct hangers on the south end; and
- began work on the PEPCO duct bank.
The construction project has been underway for 267 days.