Construction Update: August 30 to September 12, 2012

Henley Construction Company reports that they have:
  • continued perimeter channel framing; 
  • finished the slab preparation for the main and second floor;
  • completed installation of stairway two;
  • poured the concrete slab on the main and second floor decks;
  • poured a portion of stairway two;  
  • continued with duct hangers on the south end; and
  • began work on the PEPCO duct bank.

The construction project has been underway for 267 days.

Posted by R. Gale