Construction Update: September 13 to September 26, 2012

Henley Construction Company reports that they have:
  • finished perimeter steel framing except for extra at A line 5 & 6; 
  • finished pouring all slabs except at new electrical room;
  • began light gauge perimeter framing at north end and at light monitor;
  • began spray fireproofing under concrete slabs and perimeter;
  • finshed slab preparation on the first and second floors (plumbing and electrical);  
  • continued working on mechanical, plumbing and electrical conduit hangers;
  • started footing at chiller enclosure and planter at south end of basement; and
  • installed PEPCO duct bank and pull box.

The construction project has been underway for 281 days.