Construction Update: October 24 to November 7, 2012

Henley Construction Company reports that they have:
  • Started interior metal framing;
  • Completed exterior metal framing except at book drop;
  • Started installation of Stair No. 1; 
  • Started Installation of high roof;
  • Started setting air handling units at the mechanical level and in basement.;
  • Poured new electric room slab;
  • Poured chiller and generator pads;
  • Started setting boilers and pumps in basement;
  • Started hangers and duct in basement; and
  • Filled existing brick columns with concrete.

Posted by R. Gale

Construction Update: October 10 to October 24, 2012

Henley Construction Company reports that they have:
  • Poured MEP pads;
  • Continued with perimeter metal framing and start sheathing;
  • Started roof blocking (now 90% complete);
  • Continued with electrical rough-ins for all areas;
  • Finished ductwork mains at north end under slabs;
  • Started hanging duct mains on the second floor north end;
  • Finished planter/chiller enclosure concrete foundation; and
  • Finished foundation at new electrical room.
  • Roofing material is due on Friday.

Posted by R. Gale

Construction Update: September 26 to October 10, 2012

Henley Construction Company reports that they have:
  • Continued with perimeter metal framing;
  • Finished spray fire proofing under second and third decks and around perimeter framing ;
  • Poured chiller and planter walls;
  • Started roof blocking;
  • Started ductwork mains at north end under slabs;
  • Started mechanical and plumbing mains; and
  • Began overhead electrical rough-ins

Posted by R. Gale