Construction Update: October 10 to October 24, 2012

Henley Construction Company reports that they have:
  • Poured MEP pads;
  • Continued with perimeter metal framing and start sheathing;
  • Started roof blocking (now 90% complete);
  • Continued with electrical rough-ins for all areas;
  • Finished ductwork mains at north end under slabs;
  • Started hanging duct mains on the second floor north end;
  • Finished planter/chiller enclosure concrete foundation; and
  • Finished foundation at new electrical room.
  • Roofing material is due on Friday.