Construction Update: October 24 to November 7, 2012

Henley Construction Company reports that they have:
  • Started interior metal framing;
  • Completed exterior metal framing except at book drop;
  • Started installation of Stair No. 1; 
  • Started Installation of high roof;
  • Started setting air handling units at the mechanical level and in basement.;
  • Poured new electric room slab;
  • Poured chiller and generator pads;
  • Started setting boilers and pumps in basement;
  • Started hangers and duct in basement; and
  • Filled existing brick columns with concrete.