Tuesday, December 3, 2013

Working Outside the Box

mountain of boxes of books
Boxes and boxes of brand-new books, delivered Nov. 22.

Unpacking the very last box of that delivery, less than one week later. See the smiles!


Gaithersburg Library staff members have been busy unpacking, processing, sorting, and shelving the new books that will greet you when you visit us come January.  Does that caption say "very last box"?  Not quite! We'll soon be unpacking, reviewing, processing, sorting, and shelving materials from boxes stored for us in the county's warehouse.

It's a lot of work, but we know the community will be excited to see the fruits of our labor.  There's lots of good reading ahead!

The word about the library's reopening is spreading.  We had a visit from a Gazette reporter and photographer early last week.  Have you seen their story and photos?

Friday, November 15, 2013

Viewscapes

One of the first things you’ll notice upon visiting the soon-to-open Gaithersburg Library is the abundance of natural light.

Readers, browsers, and dreamers can gaze out windows in just about every section of the building, and clerestory windows frame the drifting clouds, shedding light from above.

fall color and light streaming in windows at Gaithersburg Library
Fall color and sunlight streaming in.

clerestory windows with drifting clouds
Clerestory windows with drifting clouds.

clerestory windows
Clerestory windows.

From windows on the second floor, you can see two areas of green roof, an environmentally sensitive feature of the building.  Green roofs reduce storm water runoff and heat-island effects, and they also provide insulation.  Ours are planted with sedums and other ground-hugging greenery that need only minimal maintenance.  The American Society of Landscape Architects provides an excellent explanation of the benefits of green roofs that you can share with your kids.
green roof
One of the green roof areas at Gaithersburg Library.



Tuesday, October 29, 2013

Gaithersburg Library reopening date announced

We’ll be there and we’re hoping to see you when the newly renovated Gaithersburg Library reopens on Saturday, January 4, 2014.
Invitation to Grand Reopening of Gaithersburg Library
Come for the Grand Reopening Ceremony at 9:30 a.m.  Then, throughout the day, we’ll be presenting special programming, provided with support from the Friends of the Library, Montgomery County, Inc. and the Gaithersburg Friends of the Library Chapter.  Watch the Gaithersburg Library page on MCPL’s website for announcements about these events as the day draws closer.

We’re looking forward to seeing the building full of eager new and returning library users of all ages.

Regular hours at the Gaithersburg Library will be:

Monday 9 am - 9 pm
Tuesday 9 am - 9 pm
Wednesday 9 am - 9 pm
Thursday 9 am - 9 pm
Friday 10 am - 6 pm
Saturday 10 am - 6 pm
Sunday Noon - 5 pm

Thursday, October 17, 2013

Upstairs Neighbors

When the County decided to renovate and expand the Gaithersburg Library, it designated part of the second floor for a satellite office of the Charles W. Gilchrist Center for Cultural Diversity.

The Gilchrist Center promotes cross-cultural understanding and works to connect people to needed public and private services.  It convenes services providers through networking meetings and information sharing so that organizations are aware of the resources available to Montgomery County residents and are better equipped to refer clients to needed services.

It also offers classes such as English for speakers of other languages, citizenship preparation, Spanish conversation, and basic computing.

Montgomery County Public Libraries shares the Gilchrist Center's goal of serving the County's entire diverse population, enriching the lives of all.  So we're very excited that Gilchrist Center staff and volunteers will be joining us in Gaithersburg.

Perhaps you're wondering about the man in whose honor the Center was named.  Charles W. Gilchrist served two terms as Montgomery County Executive in the late 1970's and 1980's.  Afterwards, he attended seminary and was ordained an Episcopal priest, in which capacity he continued to build community and pursue social justice.  Mr. Gilchrist recognized the importance of Montgomery County's emerging diversity and created a varied of programs that put the County on the path to becoming the welcoming community that it is today.

When we open, be sure to say "Howdy! ¡Bienvenidos! Yōkoso! Huānyíng guānglín! Hoan nghênh! Wilkommen! Ahlan wa sahlan! In kwahn deh-na meh tah! Bienvenue!" to our upstairs neighbors.  Downstairs, we'll be happy to hear it too!

Thursday, October 10, 2013

Gaithersburg Interim Library Closes October 31

The Gaithersburg Interim Library, located on the second floor of Lakeforest Mall, will close its doors on October 31.  

Its staff and materials will be redeployed as we prepare to open the newly renovated Gaithersburg Library, just a block away.  Watch for an announcement about the date of the library's grand opening, expected 8 to 10 weeks after the interim branch's closing.

October 19 is the last day you can choose Gaithersburg Interim Library as a pick-up location for holds.  If you have holds that don't arrive before the closing, edit their pick-up location in your account online.  Otherwise, when your hold becomes available, you'll be contacted to designate a new pick-up location. 

Borrowed items may be returned to any MCPL branch, and we'll soon be installing a book drop for returns at the site of the Gaithersburg Library. 

The temporary site opened its doors on December 19, 2010.  In the first nine days of service, customers borrowed more than 3,100 items.  Circulation grew so much that over 42,250 items were checked out  between April and June 2013.  The Gaithersburg Interim Library created library accounts for over 6,200 children and adults!

Until the Gaithersburg Library opens, Germantown, Quince Orchard or any MCPL branch will welcome you.

Thanks to all who made this interim facility a success.  We look forward to seeing you again at the newly renovated library.

Gaithersburg Interim Library at Lakeforest Mall shelvesGaithersburg Interim Library at Lakeforest Mall entrance

Thursday, October 3, 2013

The Shelves are Coming! The Shelves are Coming!


The Gaithersburg Library needs lots of shelves to display thousands of items that will be available to borrow. Specifically, we'll install 9941 linear feet of shelving, or 1.88 miles worth.

Two 53-foot flatbed trucks are delivering Gaithersburg Library's new shelving from Georgetown, Massachusetts, within the next couple of weeks. The trucks will travel about 475 miles with our 30 tons of shelving. You may see them unloading at the new building.

The tallest bookcases will be 66 inches, contributing to the library's atmosphere of openness. Books on the sloped bottom shelves will be canted to allow easier reading of titles and call numbers.

At the ends of some of the shelf ranges, you'll find touch-screen monitors for easy catalog searching to locate materials.

Watch this space! Each week, we'll be featuring a different aspect of the new Gaithersburg Library, its collection, technology, and services.

Friday, August 30, 2013

Construction Update: August 14, 2013-August 28, 2013

Posted by Kay Bowman

Henley Construction reports that they have:

  • Continued with flooring, all areas
  • Completed elevator installation, inspect
  • Completed toilet fixtures, all areas
  • Continued casework all areas
  • Completed resilient floor
  • Started flooring, south end
  • Continued ACT installation, all areas
  • Continued wood door/hardware installation, all areas
  • Started window blind/shade installation
  • Continued site lighting
  • Continued curb and gutter (pending site issues)
  • Finished underground at SWM-2-2, 2-3, 2-4
  • Completed pervious pavement
  • Started base paving, southwest side

Monday, August 19, 2013

Construction Update: August 1, 2013-August 13, 2013

Posted by Kay Bowman

Henley Construction reports that they have:

  • Continued Casework/Millwork Installation
  • Began flooring installation (rubber flooring at 1st floor)
  • Above ceiling inspections, all areas
  • Continued toilet fixtures, 1st/2nd floors
  • Continued toilet partition and accessories
  • Inspected elevator
  • Continued ROW installation, curb and gutter, all areas
  • Installed pervious pavement (following inspection report)
  • Installed site concrete
  • Started seed/sod
  • Continued landscaping
  • Installed pylon sign
  • Started trellis wall installation
  • Installed asphalt paths

Monday, August 5, 2013

Construction Update: July 18, 2013-July 31, 2013

Posted by Kay Bowman

Henley Construction has reported that they have:

  • Continued work on wall and soffit panels
  • Continued sunshade installation
  • Finished ceramic tile installation at lobby/Stair #1
  • Worked on resinous flooring, second floor
  • Started chiller, VAV's AHU's, all areas as needed
  • SWM 2-2, 2-3, 2-4, ongoing
  • Started fine grading around north/east sides of building
  • Began porous concrete 1-4, 1-5, 1-6
  • Installed concrete dumpster pad and handicap parking area
  • Started elevator installation

Thursday, July 18, 2013

Construction Update: July 3, 2013-July 17, 2013

Posted by Kay Bowman

Henley Construction reports that they have:

  • Installed mechanical enclosure louvers
  • Continued wall and soffit ACP panel installation
  • Installed vegetative roof tray
  • Finished mechanical, plumbing connections
  • Continued electrical, rough in and fixtures, all areas
  • Worked on ceiling grid issues
  • Continued painting in all areas
  • Completed hydro inspection for sprinkler system, 1st floor
  • Installed ceramic wall tile at central hall and main lobby
  • GWB ceilings, 1st floor
  • Started VFD, chiller, mechanical units
  • Started SWM 2-2, 2-3, 2-4

Wednesday, July 3, 2013

Construction Update: June 19, 2013-July 3, 2013

Posted by Kay Bowman

Henley Construction has reported that they have:

  • Continued with the installation of the wall and soffit panels
  • Continued with sun shade installation
  • Finished mechanical, plumbing connections and equipment installation
  • Finished interior storefront installation
  • Continued electric rough ins and fixtures, all areas
  • Continued ceiling grid installation
  • Continued painting, all areas
  • GWB Ceilings, 1st floor
  • Started mechanical units
  • Finished curb and gutter, west side
  • Finished sidewalks and steps at main entrance
  • Started prep for base coat paving

Thursday, June 20, 2013

Construction Update: June 6, 2013-June 20, 2013

Posted by Kay Bowman

Henley Construction has reported that they have:
  • Installed ACP, all areas
  • Installed sunshade
  • Installed mechanical, plumbing connections
  • Finished sprinkler rough-ins/drops necessary for hydro
  • Installed interior storefront
  • Installed electrical rough-ins, all areas
  • Installed ceiling grid
  • Continued painting, all areas
  • Started bathroom fixture installation
  • Started site lighting installation
  • Installed curb and gutter (southwest)
  • Installed sidewalks and steps

Thursday, June 6, 2013

Construction Update: May 22, 2013-June 8, 2013

Posted by Kay Bowman

Henley Construction has reported that they have

  • Installed ACP, all areas
  • Continued with sunshade installation
  • Continued installing mechanical, plumbing connections
  • Finished sprinkler rough-ins/drops for hydro
  • Installed interior storefront
  • Continued electrical rough-ins, all areas
  • Installed ceiling grid
  • Continued painting, all areas
  • Started bathroom fixture installation
  • Started curb and gutter installation, southwest
  • Started insallation of sidewalks and steps

Monday, June 3, 2013

Construction update: May 9, 2013-May 22, 2013

Posted by Kay Bowman

Henley Construction has reported that they have

  • Continued with the fiber cement panel installation
  • Started exterior aluminum wall panels and soffits, south/east
  • Installed building louvers at PH
  • Continued the sunshade installation
  • Tested building envelope
  • Continued the mechanical/plumbing connections
  • Installed interior column cover
  • Continued the mechanical/plumbing installation
  • Finished wall tile in bathrooms
  • Continued with overhead electrical rough in, all areas
  • Installed interior storefront
  • Continued interior prime and painting, all areas
  • Installed sliding automatic door
  • Installed ceiling grid, 1st floor, North
  • Started curb and gutter work
  • Started sidewalks/steps
  • Finished SWM, 1-4, 2-2, 1-6, 2-4
  • Started SWM, 1-5, 2-3

Monday, May 13, 2013

Construction Update: April 25, 2013-May 10, 2013

Posted by Kay Bowman

Henley Construction has reported that they have:
  • Continued to work on the alum composite soffits
  • Started installation of building louvers at basement
  • Continued sunshade installation
  • Tested building envelope
  • Washed down envelope masonry
  • Continued mechanical/plumbing connections
  • Continued installing ceramic wall tile in bathrooms
  • Continued interior store fronts fabrication/delivery
  • Continued hanging/finishing GWB in all areas
  • Continued with overhead electrical rough-in, all areas
  • Started interior painting, North
  • Started SWM 1-4, 2-2, 1-6, 2-4
  • Continued framing GWB ceilings
  • Completed water quality facility, #2

Tuesday, April 30, 2013

Construction Update: April 11 - 24, 2013

Posted by Kay Bowman

Henley Construction has reported that they have:

  • Completed intumescent fireproofing and repairs, 1st-3rd floors
  • Installed all exterior doors/frames (building is locked and secure)
  • Continued fiber cement panel installation
  • Completed standing seam/centria wall panel installation
  • Completed exterior curtainwall/storefront
  • Begun ceramic wall tile at bathroom walls
  • Continued hanging drywall, all areas
  • Finished sprinkler rough ins
  • Continued duct installation, south end
  • Finished framing elevator shaft, began hanging drywall
  • Finished water quality facility #1
  • Begun water quality facility #2


Wednesday, April 10, 2013

Construction Update: March 28 - April 10, 2013

Posted by Kay Bowman

Henley Construction has reported that they have
  • Completed permanent power construction
  • Finished metal roofing except trim that ties to wall panels
  • Finished all interior/exterior stonework
  • Completed pluming inspections for interior walls
  • Continued fiber cement panels
  • Continued hanging drywall in all areas, started closing walls north end, started fire taping above ceilings at north end
  • Finished paring lot demo
  • Started SWM facility #1


Thursday, March 28, 2013

Construction Update: March 14 - 27, 2013

Posted by Kay Bowman

Henley Construction Company has reported that they have:
  • Installed permanent power; waiting on final PEPCO connection
  • Completed above ceiling fireproofing
  • Completed air barriers, all areas
  • Continued with metal roof
  • Continued fiber cement cladding all elevations
  • Continued standing seam metal panels
  • Started centria panel installation
  • Completed standing seam metal roofing
  • Continued with storefront/curtain installation, 1st/2nd floors
  • Split face cmu, completed exterior stone veneer
  • Continued with pluming rough ins all areas
  • Continued with electric rough ins all areas
  • Completed most wall inspecitions
  • Continued with duct installation, south end
  • Continued with sprinkler system installation
  • Continued sheet rock all areas
  • Started demo existing parking lot west side
  • Continued building elevator shaff walls


Thursday, March 14, 2013

Construction Update: February 27 - March 13, 2013

Posted by Kay Bowman

Henley Construction Company has reported that they have:
  • Pepco set transformer and continues permanent power installation
  • Poured Stair #1
  • Continued spray fireproofing
  • Continued with air barrier, all areas
  • Continued fiber cement cladding
  • Started exterior standing seam wall panels
  • Continued with standing seam metal roof
  • Continued with curtain wall/storefront frame/glass installation
  • Completed stone veneer at retaining wall
  • Continued with interior/exterior stone veneer and split face cmu
  • Continued pluming rough in, all areas
  • Continued electric rough in, all areas
  • Continued duct work installation, all areas
  • Measured interior storefront frames/began fabrication
  • Continued sprinkler mains and branches, all areas
  • Started  hanging drywall first and second floors, north end
  • Started building elevator shaft on stair one walls
  • Continued roofing deficiency repairs, per Gale reports


Tuesday, February 26, 2013

Construction Update: February 13-February 26, 2013

Henley Construction Company has reported that they have:
  • Started upper level spray fire proofing
  • Continued with air barrier, all areas
  • Installation of fiber cement panel
  • Continued metal roof installation
  • Continued window installation
  • Continued interior stone veneer on exterior cmu
  • Continued pluming rough ins, all areas
  • Continued with electric rough ins, all areas
  • Continued with duct installation, south end
  • Started sprinkler mains and branches, 1st/2nd floors
  • Installed coiling door supports and doors, 1st/2nd floors
  • Installed switchgear
  • Connected storm lines from bldg to flow splitter 1
  • Began fixing roof deficiencies per Gail Reports

Posted by Kay Bowman

Tuesday, February 19, 2013

Construction Update: January 31, 2013-February 12, 2013

Henley Construction Company has reported that they have:
  • Finished interior spray fire proofing 1st floor SW/SE
  • Continued with air barrier
  • Continued with fiber cement system mock-up
  • Started exterior windows and curtain wall first floor
  • Finished low roof installation at green roof/canopies with exception of deficiency items
  • Continued electric rough-ins all areas
  • Started ductwork mains south west side
  • Continued with plumbing rough-in all areas
  • Started sprinkler rough-in at basement
  • Continued interior wall framing
  • Continued with stone veneer
  • Continued electric rough-ins 2nd and 3rd floors

Posted by Kay Bowman

Wednesday, January 30, 2013

Construction Update: January 17 to January 30, 2013

Henley Construction Company has reported that they have:
  • Finished low roof fireproofing 1st floor SW/SE;
  • Finished fiber cement panel mock up;
  • Started exterior window installation;
  • Finished low roof installation except some flashings around other trades;
  • Continued elect rough-in all areas;
  • Started duct work, 1st floor SW;
  • started sprinkler rough-in at basement Interior wall framing;
  • Continued interior stone veneer; and 
  • Continued electric rough-ins, 2nd and 3rd floors

Posted by Kay Bowman

Wednesday, January 16, 2013

Construction Update: January 3, 2013 to January 16, 2013

Henley Construction Company reports that they have:
  • Installed steel framing enclosure, chiller area 
  • Completed interior spray fireproofing 1st Floor SW
  • Started 1st floor SE spray fireproofing
  • Continued installing air barrier;
  • Continued interior wall framing;
  • Started mock up for fiber cement panels
  • Started window flashings
  • Continued with low roof installation
  • Continued with electric panel equipment main electric room
  • Continued testing and installing ducts
  • Continued mechanical and plumbing rough-in all areas
  • Started stone veneer, and 
  • Started  electric rough-ins on second floor.
Posted by K. Bowman
 

Tuesday, January 8, 2013

Construction Update: December 22, 2012 to January 2, 2013

Henley Construction Company reports that they have:
  • Begun low roof insulation;
  • Started interior spray fireproofing on the first foor;
  • Set the skylight;
  • Continued installing air barrier;
  • Continued interior wall framing;
  • Continued installing ducts in north end on all levels;
  • Scheduled duct testing;
  • Begun sanitary wall rough-ins;
  • Continued electrical rough-ins on north end; and
  • Started temporary heating of the building.
Posted by R. Gale
 

Construction Update: December 5-December 22, 2012

Henley Construction Company reports that they have:
  • Prepared for installation of metal at high roof/monitor roof; 
  • Contiued installing PVC low roof;
  • Begun installation of air barrier;
  • Continued duct work installation at North end of library;
  • Continued interior light gauge framing;
  • Continued plumbing and electrical rough-in for all areas;
  • Completed stone veneer sample panel;
  • Installed steel at chimney infill;
  • Started mechanical, piping in basement and chill water piping;
  • Started installing duct branches on second floor;
  • Continued installing duct branches on first floor north;
  • Started setting door frames on north end; and
  • Tied in storm water lines from roof dreains in all areas.

Posted by R. Gale

Construction Update: November 21-December 5, 2012

Henley Construction Company reports that they have:
  • Completed field measurements for exterior fiber cement panels;
  • Set emergency generator;
  • Continued working on exterior framing and sheathing;
  • Started PVC low roof installation;
  • Finished roof blocking;
  • Finished form rolling sheet metal for high roof installation;
  • Hung VAV units at 1st/2nd floor North;
  • Worked on duct main/branches at 1st and 2nd floor North;
  • Continued interior light gauge framing;
  • Continued plumbing and electrical rough-in for all areas;
  • Started window fabrication; and
  • Finished substrate for light monitor roof.

Posted by R. Gale

Construction Update: November 7-November 21, 2012

Henley Construction Company reports that they have:
  • Delivered and set the chiller;
  • Continued with interior light gauge framing;
  • Finished stair 1 installation;
  • Began fabricating high roof panels;
  • Started low roof installation;
  • Finished roof blocking;
  • Continued electrical and plumbing rough-ins;
  • Finished interior CMU walls in basement area;
  • Started field measuring for windows; and
  • Started light monitor roof. 

Posted by R. Gale