Henley Construction Company has reported that they have:
- Finished low roof fireproofing 1st floor SW/SE;
- Finished fiber cement panel mock up;
- Started exterior window installation;
- Finished low roof installation except some flashings around other trades;
- Continued elect rough-in all areas;
- Started duct work, 1st floor SW;
- started sprinkler rough-in at basement Interior wall framing;
- Continued interior stone veneer; and
- Continued electric rough-ins, 2nd and 3rd floors