Construction Update: January 3, 2013 to January 16, 2013

Henley Construction Company reports that they have:
  • Installed steel framing enclosure, chiller area 
  • Completed interior spray fireproofing 1st Floor SW
  • Started 1st floor SE spray fireproofing
  • Continued installing air barrier;
  • Continued interior wall framing;
  • Started mock up for fiber cement panels
  • Started window flashings
  • Continued with low roof installation
  • Continued with electric panel equipment main electric room
  • Continued testing and installing ducts
  • Continued mechanical and plumbing rough-in all areas
  • Started stone veneer, and 
  • Started  electric rough-ins on second floor.