Construction Update: November 21-December 5, 2012

Henley Construction Company reports that they have:
  • Completed field measurements for exterior fiber cement panels;
  • Set emergency generator;
  • Continued working on exterior framing and sheathing;
  • Started PVC low roof installation;
  • Finished roof blocking;
  • Finished form rolling sheet metal for high roof installation;
  • Hung VAV units at 1st/2nd floor North;
  • Worked on duct main/branches at 1st and 2nd floor North;
  • Continued interior light gauge framing;
  • Continued plumbing and electrical rough-in for all areas;
  • Started window fabrication; and
  • Finished substrate for light monitor roof.