Henley Construction Company has reported that they have:
- Finished interior spray fire proofing 1st floor SW/SE
- Continued with air barrier
- Continued with fiber cement system mock-up
- Started exterior windows and curtain wall first floor
- Finished low roof installation at green roof/canopies with exception of deficiency items
- Continued electric rough-ins all areas
- Started ductwork mains south west side
- Continued with plumbing rough-in all areas
- Started sprinkler rough-in at basement
- Continued interior wall framing
- Continued with stone veneer
- Continued electric rough-ins 2nd and 3rd floors