Construction Update: January 31, 2013-February 12, 2013

Henley Construction Company has reported that they have:
  • Finished interior spray fire proofing 1st floor SW/SE
  • Continued with air barrier
  • Continued with fiber cement system mock-up
  • Started exterior windows and curtain wall first floor
  • Finished low roof installation at green roof/canopies with exception of deficiency items
  • Continued electric rough-ins all areas
  • Started ductwork mains south west side
  • Continued with plumbing rough-in all areas
  • Started sprinkler rough-in at basement
  • Continued interior wall framing
  • Continued with stone veneer
  • Continued electric rough-ins 2nd and 3rd floors