Construction Update: March 14 - 27, 2013

Posted by Kay Bowman

Henley Construction Company has reported that they have:
  • Installed permanent power; waiting on final PEPCO connection
  • Completed above ceiling fireproofing
  • Completed air barriers, all areas
  • Continued with metal roof
  • Continued fiber cement cladding all elevations
  • Continued standing seam metal panels
  • Started centria panel installation
  • Completed standing seam metal roofing
  • Continued with storefront/curtain installation, 1st/2nd floors
  • Split face cmu, completed exterior stone veneer
  • Continued with pluming rough ins all areas
  • Continued with electric rough ins all areas
  • Completed most wall inspecitions
  • Continued with duct installation, south end
  • Continued with sprinkler system installation
  • Continued sheet rock all areas
  • Started demo existing parking lot west side
  • Continued building elevator shaff walls