Henley Construction Company has reported that they have:
- Installed permanent power; waiting on final PEPCO connection
- Completed above ceiling fireproofing
- Completed air barriers, all areas
- Continued with metal roof
- Continued fiber cement cladding all elevations
- Continued standing seam metal panels
- Started centria panel installation
- Completed standing seam metal roofing
- Continued with storefront/curtain installation, 1st/2nd floors
- Split face cmu, completed exterior stone veneer
- Continued with pluming rough ins all areas
- Continued with electric rough ins all areas
- Completed most wall inspecitions
- Continued with duct installation, south end
- Continued with sprinkler system installation
- Continued sheet rock all areas
- Started demo existing parking lot west side
- Continued building elevator shaff walls