Construction Update: April 11 - 24, 2013

Posted by Kay Bowman

Henley Construction has reported that they have:

  • Completed intumescent fireproofing and repairs, 1st-3rd floors
  • Installed all exterior doors/frames (building is locked and secure)
  • Continued fiber cement panel installation
  • Completed standing seam/centria wall panel installation
  • Completed exterior curtainwall/storefront
  • Begun ceramic wall tile at bathroom walls
  • Continued hanging drywall, all areas
  • Finished sprinkler rough ins
  • Continued duct installation, south end
  • Finished framing elevator shaft, began hanging drywall
  • Finished water quality facility #1
  • Begun water quality facility #2


Wednesday, April 10, 2013

Construction Update: March 28 - April 10, 2013

Posted by Kay Bowman

Henley Construction has reported that they have
  • Completed permanent power construction
  • Finished metal roofing except trim that ties to wall panels
  • Finished all interior/exterior stonework
  • Completed pluming inspections for interior walls
  • Continued fiber cement panels
  • Continued hanging drywall in all areas, started closing walls north end, started fire taping above ceilings at north end
  • Finished paring lot demo
  • Started SWM facility #1