Construction Update: April 11 - 24, 2013

Posted by Kay Bowman

Henley Construction has reported that they have:

  • Completed intumescent fireproofing and repairs, 1st-3rd floors
  • Installed all exterior doors/frames (building is locked and secure)
  • Continued fiber cement panel installation
  • Completed standing seam/centria wall panel installation
  • Completed exterior curtainwall/storefront
  • Begun ceramic wall tile at bathroom walls
  • Continued hanging drywall, all areas
  • Finished sprinkler rough ins
  • Continued duct installation, south end
  • Finished framing elevator shaft, began hanging drywall
  • Finished water quality facility #1
  • Begun water quality facility #2