Posted by Kay Bowman
Henley Construction has reported that they have
- Completed permanent power construction
- Finished metal roofing except trim that ties to wall panels
- Finished all interior/exterior stonework
- Completed pluming inspections for interior walls
- Continued fiber cement panels
- Continued hanging drywall in all areas, started closing walls north end, started fire taping above ceilings at north end
- Finished paring lot demo
- Started SWM facility #1