Posted by Kay Bowman
Henley Construction has reported that they have
- Installed ACP, all areas
- Continued with sunshade installation
- Continued installing mechanical, plumbing connections
- Finished sprinkler rough-ins/drops for hydro
- Installed interior storefront
- Continued electrical rough-ins, all areas
- Installed ceiling grid
- Continued painting, all areas
- Started bathroom fixture installation
- Started curb and gutter installation, southwest
- Started insallation of sidewalks and steps