Posted by Kay Bowman
Henley Construction has reported that they have
- Continued with the fiber cement panel installation
- Started exterior aluminum wall panels and soffits, south/east
- Installed building louvers at PH
- Continued the sunshade installation
- Tested building envelope
- Continued the mechanical/plumbing connections
- Installed interior column cover
- Continued the mechanical/plumbing installation
- Finished wall tile in bathrooms
- Continued with overhead electrical rough in, all areas
- Installed interior storefront
- Continued interior prime and painting, all areas
- Installed sliding automatic door
- Installed ceiling grid, 1st floor, North
- Started curb and gutter work
- Started sidewalks/steps
- Finished SWM, 1-4, 2-2, 1-6, 2-4
- Started SWM, 1-5, 2-3