Construction update: May 9, 2013-May 22, 2013

Posted by Kay Bowman

Henley Construction has reported that they have

  • Continued with the fiber cement panel installation
  • Started exterior aluminum wall panels and soffits, south/east
  • Installed building louvers at PH
  • Continued the sunshade installation
  • Tested building envelope
  • Continued the mechanical/plumbing connections
  • Installed interior column cover
  • Continued the mechanical/plumbing installation
  • Finished wall tile in bathrooms
  • Continued with overhead electrical rough in, all areas
  • Installed interior storefront
  • Continued interior prime and painting, all areas
  • Installed sliding automatic door
  • Installed ceiling grid, 1st floor, North
  • Started curb and gutter work
  • Started sidewalks/steps
  • Finished SWM, 1-4, 2-2, 1-6, 2-4
  • Started SWM, 1-5, 2-3