Thursday, July 18, 2013

Construction Update: July 3, 2013-July 17, 2013

Posted by Kay Bowman

Henley Construction reports that they have:

  • Installed mechanical enclosure louvers
  • Continued wall and soffit ACP panel installation
  • Installed vegetative roof tray
  • Finished mechanical, plumbing connections
  • Continued electrical, rough in and fixtures, all areas
  • Worked on ceiling grid issues
  • Continued painting in all areas
  • Completed hydro inspection for sprinkler system, 1st floor
  • Installed ceramic wall tile at central hall and main lobby
  • GWB ceilings, 1st floor
  • Started VFD, chiller, mechanical units
  • Started SWM 2-2, 2-3, 2-4

Wednesday, July 3, 2013

Construction Update: June 19, 2013-July 3, 2013

Posted by Kay Bowman

Henley Construction has reported that they have:

  • Continued with the installation of the wall and soffit panels
  • Continued with sun shade installation
  • Finished mechanical, plumbing connections and equipment installation
  • Finished interior storefront installation
  • Continued electric rough ins and fixtures, all areas
  • Continued ceiling grid installation
  • Continued painting, all areas
  • GWB Ceilings, 1st floor
  • Started mechanical units
  • Finished curb and gutter, west side
  • Finished sidewalks and steps at main entrance
  • Started prep for base coat paving