Thursday, July 18, 2013

Construction Update: July 3, 2013-July 17, 2013

Posted by Kay Bowman

Henley Construction reports that they have:

  • Installed mechanical enclosure louvers
  • Continued wall and soffit ACP panel installation
  • Installed vegetative roof tray
  • Finished mechanical, plumbing connections
  • Continued electrical, rough in and fixtures, all areas
  • Worked on ceiling grid issues
  • Continued painting in all areas
  • Completed hydro inspection for sprinkler system, 1st floor
  • Installed ceramic wall tile at central hall and main lobby
  • GWB ceilings, 1st floor
  • Started VFD, chiller, mechanical units
  • Started SWM 2-2, 2-3, 2-4

1 comment:

  1. Does not look like it's going to be finished in time for a fall opening. I live behind this building. I am sick and tired of seeing this project take forever to complete.