Friday, August 30, 2013

Construction Update: August 14, 2013-August 28, 2013

Posted by Kay Bowman

Henley Construction reports that they have:

  • Continued with flooring, all areas
  • Completed elevator installation, inspect
  • Completed toilet fixtures, all areas
  • Continued casework all areas
  • Completed resilient floor
  • Started flooring, south end
  • Continued ACT installation, all areas
  • Continued wood door/hardware installation, all areas
  • Started window blind/shade installation
  • Continued site lighting
  • Continued curb and gutter (pending site issues)
  • Finished underground at SWM-2-2, 2-3, 2-4
  • Completed pervious pavement
  • Started base paving, southwest side

Monday, August 19, 2013

Construction Update: August 1, 2013-August 13, 2013

Posted by Kay Bowman

Henley Construction reports that they have:

  • Continued Casework/Millwork Installation
  • Began flooring installation (rubber flooring at 1st floor)
  • Above ceiling inspections, all areas
  • Continued toilet fixtures, 1st/2nd floors
  • Continued toilet partition and accessories
  • Inspected elevator
  • Continued ROW installation, curb and gutter, all areas
  • Installed pervious pavement (following inspection report)
  • Installed site concrete
  • Started seed/sod
  • Continued landscaping
  • Installed pylon sign
  • Started trellis wall installation
  • Installed asphalt paths

Monday, August 5, 2013

Construction Update: July 18, 2013-July 31, 2013

Posted by Kay Bowman

Henley Construction has reported that they have:

  • Continued work on wall and soffit panels
  • Continued sunshade installation
  • Finished ceramic tile installation at lobby/Stair #1
  • Worked on resinous flooring, second floor
  • Started chiller, VAV's AHU's, all areas as needed
  • SWM 2-2, 2-3, 2-4, ongoing
  • Started fine grading around north/east sides of building
  • Began porous concrete 1-4, 1-5, 1-6
  • Installed concrete dumpster pad and handicap parking area
  • Started elevator installation