Posted by Kay Bowman
Henley Construction reports that they have:
- Continued Casework/Millwork Installation
- Began flooring installation (rubber flooring at 1st floor)
- Above ceiling inspections, all areas
- Continued toilet fixtures, 1st/2nd floors
- Continued toilet partition and accessories
- Inspected elevator
- Continued ROW installation, curb and gutter, all areas
- Installed pervious pavement (following inspection report)
- Installed site concrete
- Started seed/sod
- Continued landscaping
- Installed pylon sign
- Started trellis wall installation
- Installed asphalt paths