Henley Construction reports that they have:
- Continued with flooring, all areas
- Completed elevator installation, inspect
- Completed toilet fixtures, all areas
- Continued casework all areas
- Completed resilient floor
- Started flooring, south end
- Continued ACT installation, all areas
- Continued wood door/hardware installation, all areas
- Started window blind/shade installation
- Continued site lighting
- Continued curb and gutter (pending site issues)
- Finished underground at SWM-2-2, 2-3, 2-4
- Completed pervious pavement
- Started base paving, southwest side