Construction Update: August 14, 2013-August 28, 2013

Posted by Kay Bowman

Henley Construction reports that they have:

  • Continued with flooring, all areas
  • Completed elevator installation, inspect
  • Completed toilet fixtures, all areas
  • Continued casework all areas
  • Completed resilient floor
  • Started flooring, south end
  • Continued ACT installation, all areas
  • Continued wood door/hardware installation, all areas
  • Started window blind/shade installation
  • Continued site lighting
  • Continued curb and gutter (pending site issues)
  • Finished underground at SWM-2-2, 2-3, 2-4
  • Completed pervious pavement
  • Started base paving, southwest side