Construction Update: July 18, 2013-July 31, 2013

Posted by Kay Bowman

Henley Construction has reported that they have:

  • Continued work on wall and soffit panels
  • Continued sunshade installation
  • Finished ceramic tile installation at lobby/Stair #1
  • Worked on resinous flooring, second floor
  • Started chiller, VAV's AHU's, all areas as needed
  • SWM 2-2, 2-3, 2-4, ongoing
  • Started fine grading around north/east sides of building
  • Began porous concrete 1-4, 1-5, 1-6
  • Installed concrete dumpster pad and handicap parking area
  • Started elevator installation