Henley Construction has reported that they have:
- Continued work on wall and soffit panels
- Continued sunshade installation
- Finished ceramic tile installation at lobby/Stair #1
- Worked on resinous flooring, second floor
- Started chiller, VAV's AHU's, all areas as needed
- SWM 2-2, 2-3, 2-4, ongoing
- Started fine grading around north/east sides of building
- Began porous concrete 1-4, 1-5, 1-6
- Installed concrete dumpster pad and handicap parking area
- Started elevator installation